Tara: Pool Replacement Project
        
        
            
                - Project typeAquatic Centre
- Project scheduleProject Complete
- Completion Date19 September 2023
            
 
 
      
        Western Downs Regional Council has delivered a revitalisation of the Tara Pool which has provided a vibrant new aquatic facility for the area.
The project replaced an existing pool which was in an extremely poor condition, and enhanced a range of pool features and amenities.
The revamp supports a range of uses including Learn to Swim, squad training, representative meets, recreational swimming, and broader community get togethers. 
Key Features:
    - brand new 25 metre pool with eight wider swim lanes
- disability ramp and lane
- accessible adult change facility
- heating to extend the swim season
- pool blankets to maintain water temperature
- open communal spaces for community enjoyment
- state of the art filtration systems
- new kiosk and amenities
Support Measures for Tara Community
Council implemented a range of measures to support the Tara community while the new Aquatic Centre was being constructed (two consecutive swim seasons). These measures included:
    - Free entry to all Western Downs Regional Council pools for Tara residents
- Free Learn 2 Swim and Squad Swim Programmes for Tara residents
- Funding provided directly to the Tara Amateur Swimming Club to support travel costs to the total of $34,000. This funding is for the purpose of travel to any aquatic centre within region for the purpose of associated training and competition.
- 
    Tara residents received free entry to the revitalised Aquatic Centre until the community fun day which was held on 28 October 2023 
Project Status: Complete
Stage Outlines:
19 September 2023 - Project complete
14 February 2022 - Early site establishment and demolition works
8 December 2021 - Council endorses Taylor Builders to construct the new aquatic facility
Project Start Date:
February 2022 - Early works to remove the old pool structure and facilities to commence
March 2022 - Construction works commence
April - May 2022 - Earthworks complete
June - July 2022 - Concrete flooring and walls constructed
August - September 2022
    - Frame work for kiosk area commenced
- Pool concreting completed
- Underground electrical & plumbing services in progress
- Foundations and blockwork for the swim club/pump room commenced
September - October 2022
    - Pool tiling nearing completion
- Framework for buildings being erected
- Amenities building concrete being prepared
- Construction of roof trusses commencing
November 2022 - December 2022
    - Installation of fixings within constructed buildings
- Concrete slabs for building complete
- Frame work to be installed with trusses to follow 
January 2023 - April 2023
    - Concourse foundations 
- Undertake finishing touches to pool tiling 
- Roof framing 
May 2023 - June 2023
    - Concrete paving around pool and carpark walkway 
- Roller doors installed
- Amenities flooring and wall tiling complete 
- Pool lighting installed 
- Car park re-sealing
- Pool filtration systems established 
July 2023 - September 2023
    - Install of diving blocks, lane ropes and pool blankets 
- Final fit off for amenities block, Kiosk and Swim Club room  
- Landscaping 
- Filling of the new pool
- BBQ install
Location
42 Smallacombe Street, Tara 4421  View Map
      
        
    
        
          -27.2782785,150.4608637
        
        
          42 Smallacombe Street ,
          Tara 4421
        
        
            
            
          42 Smallacombe Street ,
          Tara 4421
         
		